Weekly Progress Report Guide
Weekly Progress Report: Example, Format and Guide
A weekly progress report explains what was completed during the week, how actual progress compares with the plan, which issues affected the schedule and what work should happen next.
Need to create a weekly progress report?
Use the Progress Report Generator to document planned progress, actual progress, activities, delays and next steps with live preview and PDF export.
What is a weekly progress report?
A weekly progress report is a structured summary of project performance during a seven-day period. It communicates completed work, schedule performance, delays, risks and the activities planned for the next reporting period.
What should a weekly progress report include?
Reporting period
Identify the project and the start and end dates covered by the report.
Executive summary
Give stakeholders a short overview of the current project situation.
Completed work
List the main activities and deliverables completed during the week.
Planned versus actual progress
Compare scheduled progress with the result achieved by the end of the week.
Key achievements
Highlight important milestones, approvals and completed deliverables.
Issues and delays
Explain blockers, schedule deviations and operational problems.
Risks and corrective actions
Document active risks and the actions assigned to reduce their impact.
Next-week priorities
Define the most important activities planned for the following week.
Weekly progress report example
Weekly Project Progress Report
Project: Conveyor Upgrade Project
Reporting period: July 6–12, 2026
Executive summary: Structural installation progressed as planned. Electrical activities were partially delayed because of late material delivery.
Planned progress: 78%
Actual progress: 72%
Completed work: Installed structural supports, completed alignment checks and finished cable tray installation in Area 1.
Key achievements: Mechanical installation milestone completed and approved by the client representative.
Issues and delays: Electrical cable delivery was delayed by two days, affecting termination activities.
Corrective action: Additional electrical labor will be assigned next week to recover part of the schedule variance.
Next-week priorities: Complete cable termination, begin functional testing and close remaining mechanical punch-list items.
Important weekly progress indicators
Planned progress
The percentage of work that should have been completed by the end of the reporting period.
Actual progress
The percentage of work that was actually completed during the project period.
Schedule variance
The difference between planned progress and actual progress.
Completed activities
The number of project activities or milestones finished during the week.
Delayed activities
Tasks that did not reach the planned completion level.
Open issues
Problems that remain unresolved and may affect future project performance.
How to write a weekly progress report
1. Define the reporting period
Confirm the week covered by the report and the project scope being measured.
2. Compare planned and actual progress
Use current project data to calculate performance and identify schedule variance.
3. Explain delays and risks
Describe the cause, impact and corrective response for each important issue.
4. Define next-week priorities
List the most important activities, milestones and recovery actions planned for the following week.
Common weekly progress report mistakes
Listing activities without progress
Explain the result achieved and how it compares with the weekly plan.
Hiding schedule delays
Report deviations early and explain their cause, impact and recovery action.
Using percentages without context
State what the percentage represents and which scope or activity it applies to.
Not defining next-week priorities
A weekly report should help the team understand what happens next.
Continue learning
Related progress guides
How to Write a Progress Report
Learn how to structure project progress reports with planned progress, actual progress, issues and next steps.
Project Status Report
Learn how to summarize project health, progress, schedule, budget, issues, risks and stakeholder decisions.
Monthly Progress Report
Learn how to summarize monthly project progress, milestones, schedule, cost, issues, risks and next-month priorities.
Frequently asked questions
What is a weekly progress report?
A weekly progress report summarizes project performance, completed work, planned and actual progress, issues, risks and priorities for the following week.
What should a weekly progress report include?
Include the reporting period, executive summary, completed work, progress comparison, delays, risks, corrective actions and next-week priorities.
How long should a weekly progress report be?
It should contain enough detail to support decisions without becoming difficult to review. One to several pages is common depending on project complexity.
Who prepares a weekly progress report?
Project managers, supervisors, coordinators, contractors, planners and site teams may prepare weekly progress reports.
Can a weekly progress report be exported as PDF?
Yes. PDF export preserves the layout and makes the report easier to share with clients, managers and project stakeholders.
Create a weekly progress report
Use the Progress Report Generator to document planned progress, actual progress, activities, delays and next steps with live preview and PDF export.